Project Status

Construction progress of Phalakhu Khola Hydropower Project

Overall Project Progress

Major Development Milestones

Civil Construction Progress

Key Progress Indicators

Land Acquisition

99%

Access Road

87%

Construction Power

95%

Crusher Plant

100%